120 multifamily rental units, retail space, and a park coming to Idaho Springs. Expected opening late 2025.

Q&A and construction schedule below.

The Fieldhouse Apartments are located at the former site of the Golddigger Football field. The apartments consist of 1 bed / 1 bath, 2 bed / 2 bath, and 4 bed / 4 bath unit types. 1000 sqft of retail space and a community park will also be developed.

Feburary - April 2025 Planned Construction

  • Finalize remaining soil import

  • Complete foundations

  • Begin building framing

Q&A

When is the project expected to be completed?

Spring or summer of 2026

When will the widening of Miner and Idaho Street occur?

Spring and summer of 2025

Complete the form if you wish to be notified with construction updates or if you wish to submit a question. We look forwarding to hearing from you.