120 multifamily rental units, retail space, and a park coming to Idaho Springs. Expected opening late 2025.
Q&A and construction schedule below.
The Fieldhouse Apartments are located at the former site of the Golddigger Football field. The apartments consist of 1 bed / 1 bath, 2 bed / 2 bath, and 4 bed / 4 bath unit types. 1000 sqft of retail space and a community park will also be developed.
Feburary - April 2025 Planned Construction
Finalize remaining soil import
Complete foundations
Begin building framing
Q&A
When is the project expected to be completed?
Spring or summer of 2026
When will the widening of Miner and Idaho Street occur?
Spring and summer of 2025